Construction Time Line
Foundation Stage ~ 20-31 Days
Stake out of lot, locates, basement excavation, plumbing trench, electrical trench, foundation cribbing, concrete footings & walls poured, concrete cure time, city foundation inspection, backfill foundation.
Framing & Rough-In Stage ~ 17-30 Days
Main house framing, windows & doors installed, plumbing, HVAC, electrical, and communications rough-in, optional: fireplace, vacu-flo, security rough-in, city framing & rough-in inspection.
Insulation & Drywall Stage ~ 11-20 Days
Insulation installation, drywall load, install drywall, roofing completion, attic insulation, taping, ceiling texture, taping sand, exterior siding start.
Finishing Stage One ~ 12-20 Days
Prime, sub-floor installation, finish carpentry, cabinet delivery and installation, drywall touch-up, final paint, optional: fireplace facing, rail installation.
Finishing Stage Two ~ 8-20 Days
Flooring installation, plumbing, HVAC, electrical, window final, cabinet tune-up, mirrors and shelves install, appliance delivery.
Home Completion ~ 12 Days
Final paint touch-up, construction clean, city occupancy inspection, orientation meeting at your new home.